3.6 Certificate of compliance. A certificate of compliance shall be required from a manufacturer in order to be listed as an
approved source of supply in MIL-HDBK-103 (see 6.6 herein). The certificate of complian ce submitted to DLA Land and
Maritime -VA prior to listing as an approved source of supply shall affirm that the manufacturer's product meets the
requirements of MIL-PRF-38535, appendix A and the requirements herein.
3.7 Certificate of conformance. A certificate of conformance as require d in MIL-PRF-38535, appendix A shall be provided
with each lot of microcircuits deliver ed to this drawing.
3.8 Notification of change. Notification of change to DLA Land and Maritime -VA shall be required for any change that
affects this drawing.
3.9 Verification and review. DLA Land and Maritime, DLA Land and Maritime 's agent, and the acquiring activity retain the
option to review the manufacturer's facility and applicable required documentation. Offshore documentation shall be made
available onshore at the optio n of the reviewer.
4. VERIFICATION
4.1 Sampling and inspection. Sampling and inspection pro c edures shall be in accordance with MIL-PRF-38535,
appendix A.
4.2 Screening. Screening shall be in accordance with method 5004 of MIL-STD-883, and shall be conducted on all devi c es
prior to quality conformance inspection. The following additional criteri a shall apply:
a. Burn-in test, method 1015 of MIL-STD-883.
(1) Test condition A, B, C, or D. The test circuit shall be maintained by the manufacturer under document revision level
control and shall be made available to the preparing or acquiring activity upon request. The test circuit shall specify
the inputs, outputs, biases, and power dissipation, as applicable, in accordance with the intent specified in method
1015 of MIL-STD-883.
(2) TA = +125C, minimum.
b. Interim and final electrical test parameters shall be as specified in table II herein, except interim electrical parameter
tests prior to burn-in are optional at the discretion of the manufacturer.
4.3 Quality conformance inspectio n . Quality conformance inspection shall be in accordance with method 5005 of
MIL-STD-883 including groups A, B, C, and D inspections. The following additional criteria shall apply.
4.3.1 Group A inspection.
a. Tests shall be as specified in table II herein.
b. Subgroups 4, 5, 6, 7, 8, 9, 10, and 11 in table I, method 5005 of MIL-STD-883 shall be omitted.
4.3.2 Groups C and D inspections.
a. End-point electrical parameters shall be as specified in table II herein.
b. Steady-state lif e test conditions, method 1005 of MIL-STD-883.
(1) Test condition A, B, C, or D. The test circuit shall be maintained by the manufacturer under document revision
level control and shall be ma de available to the preparing or acquiring activity upon request. The test circuit shall
specify the inputs, outputs, biases, and power dissipation, as applicabl e, in accordanc e wit h the inte nt specified in
method 1005 of MIL-STD-883.
(2) TA = +125C, minimum.
(3) Test duration: 1,000 hours, except as permitted by method 1005 of MIL-STD-883.